Concrete is being Poured
After some delays due to the cold weather the 1st floor slab pour is happening. There are approximately 15 operatives on site and the...
Exploring the Art of Goldsworthy
In 5SM we have been learning about the artist Andy Goldsworthy. Last week we designed some sticks, leaves and stones that we could use to...
Further Update on New build
The building is beginning to take shape with the construction of the concrete frame. The 1st floor slab pour is planned for this week,...
Independent skills for life
5SM have been practicing washing up after their drinks in the Independent Living Area at Belvue College. 5SM have also been practicing...
Ground floor gets walls - New build update
Progress has been good on site over the last couple of weeks. The builders are casting the columns and walls ground to first floor at...
Update on new build
Over the Christmas holidays Osborne have poured the majority of the ground floor slab. The hoarding around the building site has now been...