Update on new build

Over the Christmas holidays Osborne have poured the majority of the ground floor slab. The hoarding around the building site has now been installed, but still needs to be painted.

Last week Osborne completed the ground floor slab and have taken delivery of a very large crane! The crane will be used to install the concrete frame. The work on installing the frame will commence this week and should take about 8 weeks to complete.

The estimated completion date for the new building is now 28th October, 2019 however the date for completion of the internal refurbishment of the old building is still to be agreed. At this point it is unlikely that this will be completed before the start of the Ne

w Year in 2020