January 31, 2019

The building is beginning to take shape with the construction of the concrete frame.  The 1st floor slab pour is planned for this week, either Wednesday or Thursday, so the young people will really start to get a sense of the scale of the project.  There continues to b...

January 28, 2019

5SM have been practicing washing up after their drinks in the Independent Living Area at Belvue College.  5SM have also been practicing using money at the shops.

January 25, 2019

Progress has been good on site over the last couple of weeks.  The builders are casting the columns and walls ground to first floor at present with about half completed. The forecast cold weather this week may however slow things down!

The builders plan to cast the firs...

January 18, 2019

Over the Christmas holidays Osborne have poured the majority of the ground floor slab. The hoarding around the building site has now been installed, but still needs to be painted.

Last week Osborne completed the ground floor slab and have taken delivery of a very large...

January 18, 2019

5SM made glow in the dark decorations for night school. Post 16 held a night club for the evening. The theme was “Rave”.

Please reload

Featured Posts

Terrific Teams in Year 7 Team Building Day

January 27, 2020

1/10
Please reload

Recent Posts

January 24, 2020

January 24, 2020

January 24, 2020

January 24, 2020

January 24, 2020

January 24, 2020

January 24, 2020

January 24, 2020

January 23, 2020

Please reload

Archive